Operations Scheduling of Sugarcane Production Using Classical GERT Method (Part I: Land Preparation, Planting and Preserve Operations)

Nasim Monjezi, Mohammad Javad Sheikhdavoodi, Hasan Zakidizaji, Afshin Marzban, Mahmood Shomeili

Abstract


Analysis and evaluation of agricultural systems use these criteria: energy, economic, agronomy, environmental conservation and time. Because of time importance indicator for reducing timeliness cost, project scheduling techniques are used. Graphical Evaluation and Review Technique (GERT) is widely used as a tool for managing projects. In this research GERT Networks were used and operations scheduling of sugarcane production (land preparation, planting and preserve operations) in Khuzestan province of Iran as a case study was analysed, by using WinQsb software. Critical activities, events and path were determined. The earliest project completion time is 214.03 days. The results show a high potential for operations scheduling of sugarcane production.


Full Text:

PDF


DOI: https://doi.org/10.5296/jas.v3i2.7420

Refbacks

  • There are currently no refbacks.


Copyright (c) 2015 Nasim Monjezi, Mohammad Javad Sheikhdavoodi, Hasan Zakidizaji, Afshin Marzban, Mahmood Shomeili

Creative Commons License
This work is licensed under a Creative Commons Attribution 4.0 International License.

Journal of Agricultural Studies   ISSN 2166-0379

E-mail: jas@macrothink.org

Copyright © Macrothink Institute

To make sure that you can receive messages from us, please add the 'macrothink.org' domain to your e-mail 'safe list'. If you do not receive e-mail in your 'inbox', check your 'bulk mail' or 'junk mail' folders.

If you have any questions, please contact jas@macrothink.org.

------------------------------------------------------------------------------------------------------------------------------------------------------